CO129-626-10 Constructions of piers to improve communications 1-2-1950 - 28-2-1951 — Page 12

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All

FINANCIAL SUMMARY

1. Administering Authority -

2.

3.

Allocation

Classification

4.

Description of Scheme

12

Hong Kong Government.

Hong Kong

Communications: Ports Harbours

and Water Transport.

Construction of 2 piers and

ancillary works in fishing villages on outlying islands of the Colony.

£48,883 (8782,120).

5.

Total Cost

6.

Colonial Development and Welfare

Assistance required

Further Grant of £48,883.

7.

Estimate of assistance required:-

1951/52

Capital

£

Personal emoluments etc.

3,258

Cheung Chau Pier

19,375

Tai O Pier

26,250

£48,883

8.

(a) The project will take 9 months to complete. £1,600 worth of

steel has been imported and is available from Government stock.

(b) Local cement will be used.

(c) All equipment needed is available in the Colony.